The Emirates Nuclear Energy Corporation (ENEC) has used about 250,000 tons of reinforced steels bars in the construction of the four units. (39,000 tons). The cables used at the Barakah nuclear power plant have reached 1559 kilometers, which is more than the distance between London and Rome, which is estimated at (1433 km).
The Emirates Nuclear Energy Corporation confirmed that by the end of January, the completion rate of stations was more than 94% in the first station, 82% in the second station, 68% in the third and 41% in the fourth station, while the total achievement of the project 76%.
The Executive Committee of the Executive Council of the Emirate of Abu Dhabi, during its recent meeting chaired by *Jassim Al Zaabi, Chairman of the Committee, estimated the project that link the electric power generated by the Barakah nuclear power station to the electricity network in the Emirate at a cost of AED 63 million.
The Barakah Nuclear Power Plant comprises 4 nuclear power reactors (APR1400), one of the world’s most advanced nuclear power reactors, which meet the highest international safety and performance standards. Also it combines the latest design Between the latest developments in safety and performance technologies proven efficiency after decades of operation,
The strategic role of nuclear energy at the 2019 World Energy Congress
The World Energy Congress is the premier event of the World Energy Council, held every three years in selected cities and is the world’s largest