Taiwan’s first Nuclear Decommissioning Program

Taiwan Power Company (“Taipower”) said that Shimen Nuclear Power Plant Unit 1 will be officially shut down from December 6 and finally enter the decommissioning stage.

This unit has been in operation for 40 years. It is a boiling water reactor with an installed capacity of 636 MWe. Since the commercial operation, it has generated electricity about 162.5 TW/h. It is the first reactor in Taiwan to enter the decommissioning stage.

The decommissioning work consists of four phases:

Stage 1–“post-run transition” period, spent fuel will be transferred from the core to storage tank, which is expected to last for 8 years. It needs to survey the site and to form a project plan. In addition, the reactor cooling system will be vented and decontaminated. During this time, an independent spent fuel storage unit (ISFSI) and a radioactive waste storage area will also be constructed.

Stage 2 – Decontamination and Demolition – Transferring of spent fuel to ISFSI. Removing the reactor pressure vessel, the internal components of the reactor, and the piping of the reactor cooling system. In addition, the spent fuel storage tank and the primary side containment structure will be dismantled and then to decontaminate the concrete and plant. Also, removing large equipment from the turbine plant. This phase of work is expected to take 12 years.

Stage 3—It is expected to last for three years. The reactor building and the steam turbine plant will be dismantled and the site will be surveyed in the end.

Stage 4–the on-site recovery. It is scheduled to end in 2043. Demolition of other plants to restore the site totally.

NβN tip: Shimen Nuclear Power Plant, as the first reactor facing decommissioning, it requests lots of equipment and techniques regarding dismantling and waste treatment. It means in this market, it has broad business opportunities.

Elaine Li

Elaine Li

Elaine Li (李益楠) is Marketing Manager for the Chinese Market. With ten years of experience in the nuclear power market, Elaine is experts for the certification of safety equipment (HAF 604 and 601) and marketing intelligence.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Don’t Stop Here

India’s Fast Breeder Reactor

India’s first Indigenous Prototype Fast Breeder Reactor (PFBR) located at Kalpakkam, around 80 km from Chennai, which was ready to be commissioned in September 2015,

CGN’s Marine Nuclear Ambition

China’s nuclear heavyweight—China General Nuclear Group(“CGN”) announced in a recent press conference in Shenzhen the purchase of the pressure vessel for its ACPR50S experimental reactor

Scroll to Top