The schedule for the operation of El Dabaa nuclear power plant

The Egyptian Nuclear Power Plants Authority (NPPA), in cooperation with Rosatom, the Russian company responsible for establishing the first nuclear power plant in Egypt, has prepared the schedule for the operation of El Dabaa nuclear plant.

The following is the timetable for operating the four nuclear reactors at El Dabaa NPP:

  • February 9, 2026: the date for operating the first reactor.
  • August 12, 2026: date for operation of the second reactor.
  • August 12, 2027: operating the third reactor.
  • February 9, 2028: operating the fourth reactor.

The nuclear plant to be built in the city of El Dabaa in Matrouh Governorate, on the shores of the Mediterranean, about 130 km northwest of Cairo, includes four power units with a capacity of 1.2 GW each (4.8 GW total planned capacity), featuring the 3+ generation reactors type (VVER 3+).

Source

Aasem Abuzeid

Aasem Abuzeid

Aasem Abuzeid is the Director for MENA Region. He acts as a leading marketer in Arabic-speaking countries. He is also the COO and lead-developer of NBN.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Don’t Stop Here

SNERDI strategic agreement with CNEC

At the end of May, Mr. Zheng Mingguan, the director of Shanghai Nuclear Engineering Research and Design Institute(SNERDI)signed a strategic cooperation framework agreement with Mr.

Turkey energy mix in 2019

Turkey energy goals in 2019 are investment in waste to energy, renewal of the energy sector and reinforcement of its position in the international energy trade.

Scroll to Top