Equipment Procurement of Zhangzhou nuclear power plant

At the end of last year, the comprehensive mobilization meeting and project start-up meeting of the equipment procurement for Zhangzhou nuclear power plant was held in Fujian Province.

This project has been polished for almost four years:from July 2014 to June 2018, from the technical route of AP1000 to Hualong No.1. Zhangzhou finally sketched its trajectory with the formal approval of two evaluation reports for Hualong technology.

This meeting revealed the planning and management of equipment procurement management regarding Zhangzhou project. Particularly, as Zhangzhou NPP would be the reference model for the subsequent Hualong Production, which creative measures with respect to procurement management should be taken becomes the main topic of this conference.

At present, Zhangzhou procurement team has completed contract signing of some main equipment such as pressure vessels, main pumps and steam turbine generator assembly. And meanwhile, other equipment contracting work has been launched as planned. Up to now, 59 contracts have been nailed down.

 

NβN tip: Zhangzhou project features the technology of Hualong No.1. Suppliers at home and abroad could check with the official website of Zhangzhou Nuclear power plant for the information about the procurement procedures.

Elaine Li

Elaine Li

Elaine Li (李益楠) is Marketing Manager for the Chinese Market. With ten years of experience in the nuclear power market, Elaine is experts for the certification of safety equipment (HAF 604 and 601) and marketing intelligence.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Don’t Stop Here

Boris Arseev

Member of the Board of Directors of JSC Atomenergomash, He graduated from Ural Polytechnic Institute in 1993 with a specialization in “Thermophysics, automation and ecology

Scroll to Top