Reinforcement of the soil for Bushehr 2

The contract for the establishment of two new nuclear power units at the Bushehr nuclear power plant between Russia and Iran was signed in November 2014. For units 2 and 3, they will be supplied with the Russian VV-1000, safety requirements.

The Bushehr-2 project, according to the Iranian side, is worth about USD 10 billion and is expected to take 10 years to complete. The inauguration ceremony of the Bushehr-2 project was held on 10 September 2016.

After the excavation work which started on September 2017, Rosatom officialised the mechanically stabilized earth work in Bushehr 2 last month(May 3rd), before the first concrete day (FCD) which is planned for the third quarter of 2019.

This reinforcement of the soil is essential to strengthen the construction basis, and ensure resilience to the weather conditions and possible earthquakes.

According to the statement, the drilling of the land is scheduled to begin for the construction of power unit No. 3 in 2018, indicating that all work is in line with the timetable.

Bushehr is one piece of the newbuild in Iran. Still in May the Iranian Foreign Minister Mohammad Javad Zarif Khonsari visited Beijing to discuss other nuclear deals with China.

Arnaud Lefevre

Arnaud Lefevre

Arnaud Lefevre is the Chief Executive Officer of Dynatom International. Arnaud is in charge of the international development of the business portfolio.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Don’t Stop Here

Andrey Nikipelov, CEO of Atomenergomash

Since 2004, Andrey Nikipelov has held leading positions within nuclear industry companies 2001-2003  – Deputy General Director of JSC  “Volgograd Tractor Plant”,  Director General of Foreign Trade Company

Nuclear Talents Enrolment

On January 16, Tsinghua University signed a co-culture agreement with the State Power Investment Corporation and the China General Nuclear Corporation to educate the international

Scroll to Top