Sanmen Nuclear Power Project Unit 3 and 4 project information disclosure

The project consists of the construction of Sanmen Nuclear Power Co., Ltd.

This project is the expansion project Sanmen nuclear power project, located in Sanmen Nuclear Power Plant Units 1 and 2 on the eastern side expansion side. The construction period for units 3 and 4 will be 56 months with an interval of 10 months between both units. The site is under the supervision of Taizhou City Government (Zhejiang).

The Committee of Experts of the Ministry of Environmental Protection (NNSA) approved the site safety analysis reports, the environmental impact assessment report and the technical review.

The National Electric Power Planning and Design Institute reviewed the Feasibility study report. In terms of project preparation, the preliminary design and construction drawing design required for the project is finished. The Project enters now in the procurement phase and supply chain.

Contact for further information:

Zhejiang Sanmen Nuclear Power Co., Ltd.

Tel: 0576-81326693

Fax: 0576-81325555

E-mail: [email protected]

 

Arnaud Lefevre

Arnaud Lefevre

Arnaud Lefevre is the Chief Executive Officer of Dynatom International. Arnaud is in charge of the international development of the business portfolio.
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

Don’t Stop Here

Actual energy projects in Turkey

Veysi Kaynak, Turkish Deputy Prime Minister mentioned the current energy projects in the General Assembly on 1st of July: Nuclear Power Plants are of great

CNEC sits on a ton of cash

China Nuclear Engineering Corporation (CNEC) recently announced the total value of its newly signed nuclear contracts this year from January to September : 11.70 billion

Scroll to Top